VANCOUVER, BC — Conifex Timber announced that, in light of imminently expected transportation challenges that will affect all Canadian lumber producers for an unspecified period, together with already existing unfavourable market conditions, Conifex is reducing its sawmill operating schedule at its Mackenzie, British Columbia site to a one-shift basis for the foreseeable future and temporarily curtailing its power plant, each commencing on August 26, 2024. We anticipate an end to the curtailment of our power plant by September 30, 2024. …“Unfortunately, a reduced operating schedule at the sawmill is necessary for the foreseeable future due to the combined impact of our inability to ship production on a two-shift basis to end markets for an unspecified timeframe, reduced demand for our lumber products, low lumber prices and punitive lumber export duty impositions,” said Andrew McLellan, President and COO of Conifex.